How the kanban calculator works
The loop has to hold enough parts to cover demand while a container is being replenished. The calculator multiplies demand by the replenishment lead time, adds the safety allowance and divides by the container size.
Rounding up gives whole cards. Authorized stock is the number of cards times the container size, spread across the whole loop, not held at one location. The kanban calculation guide explains each term.
D demand per time unit, L replenishment lead time, s safety allowance, C units per container.
Worked example
Load the example. A part is used at 200 units per working hour, replenishment takes 1.5 hours, the team allows 20% extra coverage and containers hold 20 units.
| Step | Calculation | Result |
|---|---|---|
| Coverage | 200 × 1.5 × 1.20 | 360 units |
| Cards | 360 ÷ 20 | 18 cards |
| Lead time 2 hours | 200 × 2 × 1.20 ÷ 20 | 24 cards |
How to read your result
More cards mean more stock and a longer queue in front of the consuming process. If the loop needs many extra cards, the replenishment time is usually the problem. Shorter changeovers and smaller batches shrink the loop; see SMED and Little’s Law.